MAMQ | Muhammad Amin Muhammad Qaseem (Private Limited) https://mamq.com.pk The Custom Consultancy and Logistics Mon, 01 Jul 2019 06:49:32 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 MAMQ Delivers Patrind Transformers https://mamq.com.pk/de-celebrates-40-years/ https://mamq.com.pk/de-celebrates-40-years/#respond Mon, 02 May 2016 09:49:03 +0000 http://mamq.com.pk/?p=170

Paksitani transportation firm Muhammad Amin Muhammad Qaseem has completed delivery of a cargo of two 70-tonne transformers to the Patrind Hydro Power Project.

The consignment was collected from a warehouse in Islamabada and was moved to the Patrind site on eight multi-axle platforms with a push-and-pull configuration of prime movers. Due to the difficult terrain and danger of landslides, the project team reinforced large parts of the sliding area track with 10 tonnes of steel plates so the transformers could move forward easier.

“The two transformers arrived at Karachi Port and were transported to the MAMQ warehouse in Islamabad with one transformer on a 12 multi-axle platform and the other one on an 8 multi-axle platform,” said Waseem Abbasi, MAMQ Project Manager.

MAMQ is a member of the Project Cargo Network, or PCN, a global network comprising 221 specialist members and employing 16,756 staff in 102 countries.

]]>
https://mamq.com.pk/de-celebrates-40-years/feed/ 0
MAMQ Complete Challenging Transportation of Transformers in Pakistan https://mamq.com.pk/de-celebrates-41-years/ https://mamq.com.pk/de-celebrates-41-years/#respond Fri, 29 Apr 2016 15:04:22 +0000 http://mamq.com.pk/?p=159

Muhammad Amin Muhammad Qaseem (MAMQ) in Pakistan are pleased to report the recent transportation of 2 x 70tn transformers for the Patrind Hydro Power Project. The operation was made particularly challenging due to the difficult terrain on the journey to the final destination.

MAMQ Project Manager, Waseem Abbasi explains; “The 2 transformers arrived at Karachi Port and were transported to the MAMQ warehouse in Islamabad with one transformer on a 12 multi-axle platform and the other one on an 8 multi-axle platform.

From our warehouse in Islamabad, the transformers were moved to the Patrind site on 8 multi-axle platforms with a push & pull configuration of prime movers due to the high altitude terrain. Part of the journey (pictured in the thumbnail gallery below showing photos of the full operation) was some of the toughest and dangerous terrain we have faced because it is a land sliding area throughout the year. To proceed, we reinforced most of the sliding area track with 10tns of steel plates so the transformers could move forward easier and we successfully crossed the area and delivered the cargo to the dam site safely as a ‘zero defect operation’.

The Patrind Hydro Power Project has a capacity of 147mw and is located on the boundary of Azad Jammu & Kashmir (AJK) and Khyber Pakhtunkhwa near to the city of Muzzafarabad and at a distance of around 120km from Pakistan’s capital Islamabad.”

]]>